Note:
If the initial and confirmation settings are different,
• grid code selection is cancelled
• the wizard recommences step 5
If initial and confirmation settings match, but are incorrect, contact service.
Step 6 of 7: Replication
To replicate the settings from steps 1 to 6 to other inverters in the same network
• Select inverters
• Click [Replicate]
Note:
When the PV configuration, installed PV power and PV array area of follower inverters in the
network differ from that of the master, do not replicate. Set up the follower inverters individ-
ually.
Illustration 3.7: Step 6 of 7: Replication
Step 7 of 7: Inverter startup
The inverter will start automatically when the installation sequence is complete (see the
TripleLynx CN Installation Manual), and solar radiation is sufficient.
The startup sequence, including self-test, takes a few minutes.
3. Web Server Quick Guide